Before 2021, most mid-sized Indian hospitals bought medical oxygen in cylinders or as liquid oxygen (LMO) and gave it little thought. The COVID-19 second wave changed that overnight. Since then, an on-site Pressure Swing Adsorption (PSA) plant, which makes oxygen from atmospheric air, has become a standard part of hospital planning, and many states and accreditation assessors now look for a resilient on-site supply.
A PSA plant is not a plug-and-play appliance. It has to be sized correctly, meet pharmacopoeial purity, feed a properly designed medical gas pipeline, and be backed by a second source for the day it fails. This guide covers all of that, plus licensing and 2026 costs. For the wider MEP picture, see our ICU design guide, where oxygen demand is highest.
In this guide ▾
- PSA produces "Oxygen 93%", recognised in the Indian Pharmacopoeia with a purity range of 90–96% (93±3%) and limits on impurities such as CO2 and CO. It is not the same as 99.5% liquid oxygen.
- Size the plant on your real bed mix and peak demand: ICU and ventilator beds use far more oxygen than ward beds. Derate for Indian summer temperatures and humidity.
- Never rely on PSA alone. Keep an automatic changeover to a backup source, either an LMO tank or a cylinder manifold.
- Licensing depends on what you do. Filling cylinders brings drug manufacturing and PESO requirements. A captive plant feeding only your own pipeline is simpler, but confirm with your state drug controller and fire authority.
- Indicative 2026 cost is roughly ₹30 lakh–1.5 crore for the plant itself, depending on capacity, plus the pipeline, manifold room and backup supply.
How a PSA oxygen plant works
A PSA plant compresses filtered air and passes it through beds of zeolite molecular sieve, which adsorb nitrogen under pressure and let oxygen through. Two beds alternate, one producing while the other is depressurised to release nitrogen, giving a continuous oxygen flow into a buffer tank and then into the hospital pipeline.
A complete system includes an oil-free air compressor, air dryer and filtration, twin PSA columns, an oxygen buffer tank, an online purity analyser with automatic cut-off, a final bacterial filter, and a PLC control panel with alarms.
Purity: what “Oxygen 93%” means
| Parameter | Oxygen 93% (PSA) | Liquid medical oxygen (LMO) |
|---|---|---|
| Oxygen content | 90–96% (93±3%) per the Indian Pharmacopoeia | Typically 99.5%+ |
| How it’s produced | On site, from air, by molecular sieve | Cryogenic distillation at a gas plant, delivered by tanker |
| Supply risk | Depends on your power and maintenance | Depends on tanker logistics and suppliers |
| Typical use | Primary pipeline supply for wards and ICUs | Primary or backup supply. Common in large hospitals |
The Indian Pharmacopoeia lists Oxygen 93% separately from standard medical oxygen, with limits on impurities including carbon dioxide and carbon monoxide. Your plant needs a continuous purity analyser that automatically switches to the backup source if purity falls out of range. Outlets fed by PSA are often labelled “Oxygen 93%” so clinicians know what they are delivering.
Sizing the plant for your hospital
Undersizing is the most common and most dangerous mistake. Size on peak demand, not average:
- count oxygen points by type: ventilator and ICU beds, HDU beds, oxygen-supported ward beds, OTs, emergency bays and recovery;
- apply a realistic flow per point. ICU and ventilator beds draw far more than ward beds, and high-flow nasal oxygen draws more again;
- apply a diversity factor (not every point runs at full flow at once), but plan a surge scenario too. The pandemic showed that ward beds can suddenly all need oxygen;
- derate for climate: output falls in hot, humid conditions, so check the vendor’s rated output at your site’s summer temperature;
- plan for growth: leave space and pipeline capacity for a second unit if you will add beds.
Capacity is usually quoted in litres per minute (LPM) or Nm³/hr. Ask your MGPS designer to produce a written demand calculation with every assumption stated. Don’t accept a capacity simply suggested by the vendor.
Vendor brochures often state output at standard conditions. Ask for guaranteed output and purity at your site's peak summer temperature and humidity, and write it into the purchase contract.
Backup supply and pipeline design
A PSA plant depends on power, compressors and maintenance, and any of them can fail. Your oxygen design needs layers:
- primary: the PSA plant, on generator-backed power;
- secondary: an LMO tank (for larger hospitals) or a cylinder manifold, with automatic changeover when pressure or purity drops;
- reserve: an emergency cylinder bank and portable cylinders for critical areas;
- medical gas pipeline system (MGPS): copper piping, zone valve boxes on each floor, area alarm panels at nursing stations, and outlets to recognised standards;
- a manifold room sited for safe access, ventilation and tanker or cylinder delivery, away from ignition sources and oil.
Oxygen-rich environments raise fire risk, so the MGPS and manifold areas should be reviewed as part of your fire safety plan. Our equipment procurement team and MEP partners design the plant, backup and pipeline as one system.
Licences and approvals
Requirements depend on what your plant does, and state practice varies, so treat this as a checklist to confirm rather than a final answer:
| Activity | Typical approvals to check |
|---|---|
| Captive PSA feeding only your own pipeline | Confirm with the state drug controller whether any drug licence applies. Electrical safety, fire NOC update, and building or structural approval for the plant room |
| Filling oxygen cylinders (for your own use or for sale) | Drug manufacturing licence under the Drugs and Cosmetics Act (medical oxygen is a drug), and PESO approvals for cylinder filling and storage |
| LMO tank as backup | PESO licence for cryogenic storage, with site layout and safety distances |
| Large cylinder storage | PESO licence above the prescribed quantity thresholds |
Buy from vendors who can document compliance with recognised standards and pharmacopoeial purity, and keep commissioning test reports, purity logs and maintenance records. Assessors will ask for them.
Planning a hospital oxygen system?
Get a demand calculation, PSA + backup design and 2026 cost estimate.
What does a hospital PSA plant cost in 2026?
| Plant size (indicative) | Typical hospital fit | Indicative plant cost |
|---|---|---|
| Small (~100-250 LPM) | Nursing home or 30-50 bed hospital with a small ICU | ₹30–60 lakh |
| Medium (~250-500 LPM) | 75-150 bed hospital | ₹55 lakh–1 crore |
| Large (~500-1,000 LPM) | 150-300 bed hospital with large ICUs | ₹90 lakh–1.5 crore+ |
Running costs are mainly electricity for the compressor, plus annual maintenance, sieve replacement over the plant’s life, and filter changes. Compare total cost of ownership against your current LMO or cylinder spend before deciding. For full hospital budgets, see our cost per bed guide.
Planning checklist
- Count oxygen points by type and prepare a written demand and surge calculation.
- Specify output and purity at your site’s peak summer conditions.
- Design layered supply: PSA primary, LMO or cylinder secondary, emergency reserve.
- Design the MGPS with zone valves, area alarms and labelled outlets.
- Put the plant on generator-backed power with a dedicated feeder.
- Confirm licensing with the state drug controller, PESO and the fire authority for your exact use.
- Commission with purity and pressure tests, and keep logs from day one.
- Sign an annual maintenance contract with guaranteed response times.
Frequently asked questions
Is PSA oxygen safe for ICU and ventilator patients?
Oxygen 93% from a properly maintained PSA plant is recognised in the Indian Pharmacopoeia and is widely used for hospital pipeline supply, including in ICUs. The plant must hold purity within the specified range, monitor it continuously, and switch automatically to a backup source if purity drops.
Do I need a drug licence for a hospital PSA plant?
If you fill cylinders, medical oxygen is treated as a drug and a manufacturing licence is required, along with PESO approvals for filling and storage. For a captive plant feeding only your own pipeline, practice varies by state, so confirm with your state drug controller before commissioning.
Can a PSA plant fully replace liquid oxygen?
It can be the primary source, but it should never be the only one. Keep an LMO tank or cylinder manifold with automatic changeover, plus an emergency cylinder reserve, because the PSA plant depends on power and maintenance.
How do I size a PSA plant for my hospital?
Count oxygen points by type (ICU/ventilator, HDU, ward, OT, emergency), apply realistic flows and diversity, add a surge margin, and derate for local summer conditions. Have your MGPS designer produce a written calculation rather than relying on a vendor's suggestion.
What are the running costs of a PSA plant?
Mainly electricity for the air compressor, plus annual maintenance, filter changes and eventual replacement of the zeolite sieve. Many hospitals find PSA cheaper per cubic metre than bought-in oxygen at steady demand, but compare your own figures.
Plan your hospital oxygen system with Hospertz
Demand calculation, PSA and backup design, MGPS and approvals, as part of complete hospital MEP planning.
Keep reading
Cost figures are indicative 2026 planning ranges, not quotations. Pharmacopoeial specifications, PESO and drug-licensing requirements and state practice change from time to time, so confirm current requirements with your MGPS designer and the relevant authorities. This article is general information, not engineering or legal advice.
Get a demand calculation and system design from our team.